Crystal Palace have set out the next stage of their plans to transform the Main Stand at Selhurst Park, with major groundwork scheduled to progress during the November international break. The redevelopment is intended to increase the stadium’s capacity from 26,000 to more than 34,000 and introduce additional general admission seating, improved corporate facilities, better disabled access, a club museum and new community spaces.

The next phase will involve extensive excavation of the club car park, with heavy machinery brought in for the foundations. The temporary Fanzone, including its screen and stage, will be taken down, while a substantial section of the Directors car park will also be dug up. Palace are assessing possible alternative locations for the Fanzone and say supporters affected by changes to parking arrangements will be contacted.

New site barriers and pedestrian routes will be installed to protect supporters, while a substation and transformer beneath the Holmesdale Stand will be constructed and brought into use. Large water-storage tanks will also be placed beneath the Fanzone footprint, with capacity for almost one million litres to help manage flood risk during and after the project.

Once that work is complete, Palace expect the main foundation operation to begin with 500 piles driven deep into the ground. The piles will have a combined length of around 12 kilometres and are designed to withstand loads of up to 670 tonnes. Their installation is expected to take several months and will establish the foundations for the new stand.

The club has also confirmed that it has completed the purchase of all six houses on Wooderson Close, with the residents rehoused. The properties can now be prepared for demolition, with part of the land set to accommodate the south-eastern corner of the stand, a construction zone and future access routes to the stadium estate. Other enabling work includes new changing facilities beneath the Holmesdale Stand for match officials and visiting teams, alongside the relocation of cables and other infrastructure.

Palace’s redevelopment remains in its final planning phase, with discussions involving contractors continuing and construction targeted for the conclusion of the 2024/25 season. The design is intended to be built around the existing structure so the stadium can remain operational, although some hospitality areas, offices and changing facilities will temporarily move. The club has thanked Croydon Council for its continued assistance as it works towards delivering a modernised Selhurst Park for supporters and the wider south London community.